Bonds needed for plant overhaul - Tucson Local Media: Pima Pinal

Bonds needed for plant overhaul

Print
Font Size:
Default font size
Larger font size

Posted: Wednesday, November 19, 2008 12:00 am

The plan to overhaul Pima County’s main sewage treatment facilities has three “major components,” according to Jackson Jenkins, deputy director of the county’s treatment division.

Work already has begun building a 5-mile “interconnect” (or pipe) that would divert sewage from the aging Roger Road treatment plant to the newer facility off Ina Road, Jenkins said.

The Ina plant “has all the extra capacity,” he said, explaining the rationale for diverting sewage from the Roger Road facility.

Built in 1951, the Roger Road plant is essentially “three different plants pulled into one, with different eras of technology,” Jenkins explained.

County officials decided it would be “cheaper to build a new plant” than to remodel the Roger Road facility, Jenkins explained.

The new Roger Road plant would accommodate 32 million gallons of sewage per day, slightly smaller than the current facility’s payload.

The Ina campus basically includes two facilities — a late-1970s unit that can treat up to 25 million gallons of sewage per day and a more recently built facility that treats 12.5 million gallons per day.

But, the county plans to expand the Ina Road campus to a capacity of 50 million gallons per day, Jenkins said.

All the work is part of a major plan by the county to bring its major treatment facilities into compliance with federal environmental standards for lower levels of toxins, mainly nitrogen.

The county has until 2014 to upgrade and expand its Ina Road plant and until 2015 to build a new Roger Road plant.

“The ratepayers are going to have to bear those costs,” Jenkins explained.

The county has 260,000 sewer service customers, who pay an average of $23.62 per month. That monthly bill will almost double to help pay for the work, Jenkins said.

The county, however, will have to seek voter approval in the coming years for several bonds to finance the construction costs, which likely will top $1 billion.

But, county officials this month asked for a five-year extension to meet regulatory requirements for the treatment of effluent.

“The more time we have, we can minimize the cost,” Jenkins said. “We don’t have very much fluff in the schedule.”

© 2016 Tucson Local Media. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Welcome to the discussion.

Clutch - X-Ray Visions

More Featured Videos

Featured Videos

Spacer4px

Online poll

The Marana capital improvements improvements are expected to take years to complete as Marana finds the best plan of action to complete the projects and fund the improvements. Do you think this is a good idea?

The town of Marana is looking at ways to do capital improvements to the oldest neighborhoods in Marana. Over the next few months the town will survey older neighborhoods and see what amenities they need and form a plan to make sure neighborhoods have paved roads, sidewalks, adequate drainage, lighting and even pocket parks. “We want to make sure that every neighborhood has a base standard for infrastructure,” said Marana Town Manager Gilbert Davidson. The improvements are expected to take years to complete as Marana finds the best plan of action to complete the projects and fund the improvements. Do you think this is a good idea?

Total Votes: 18

Loading…

How do you feel about a potential memorial art project to honor our community’s bravest men and women?

During the Jan. 20 town council meeting, a vote was unanimously passed to look into the feasibility of a “Memorial Public Art Project,” at the request of Oro Valley resident Dick Eggerding to potentially be placed somewhere in the town to honor military veterans and first responders. Though no concrete plans were then ready to act on, there was a show of overwhelming support for such project from residents and staff alike during the council meeting. In an effort to poll to community at-large, The Explorer would like to know how you feel about a potential memorial art project to honor our community’s bravest men and women.

Total Votes: 31

Loading…

Follow us on Facebook